Integrated Cancer Center, New Hospital Complex (phase 1), Québec
Within the biggest hospital server room in Eastern Québec, Pagui is installing a structured cabling network of approximately 5,000 network cables, 92 fibre optic links and 12 secondary telecommunications rooms.
Our team is also supplying about twenty cabinets and cable shelves and containment. We are also installing a network of 12,000 hooks on every floor and an access control cabling network.
To accelerate the progress of the work, our team is working on two shifts. For this major project, we ensure very good cooperation with the client and the suppliers, because coordination of a site on this scale is complex.
Pagui is performing this project according to the BIM approach.
Location: Québec, Québec
Client: Société québécoise des infrastructures / Pomerleau