Service Stations,

Fuel Station Replacement in the Botanical Garden Service Yard

SM Construction was commissioned for the dismantling and modernization of the Botanical Garden’s fuel station. The project included:

- Removal of existing underground tanks and safe management of contaminated soil and liquids in compliance with environmental standards.
- Supply and installation of a 35,000 L above-ground tank for gasoline and diesel.
- Factory prefabrication of stainless steel piping.
- Complete civil works, including concrete slab construction and installation of protective bollards.
- Integration of on-site electrical and control systems to ensure functionality and safety of the new station.

This project reflects our commitment to delivering reliable, standards-compliant solutions while respecting timelines and client requirements.

Location: Montreal

Client: City of Montréal

Type of project: Service Station

Scope: $200,000 - $300,000

The project in pictures